Croatian Dalekovod to Engage in Big Job For Norwegian Client
As Poslovni Dnevnik/Suzana Varosanec writes, the latest job that Dalekovod has got its hands on, with the proviso that the contract will be concluded after the final confirmation, concerns the construction of a new 420 kV transmission line over in Norway, more specifically on the Aurland - Sogndal section, spanning a total length of 41 kilometres.
After an evaluation process in accordance with the tender criteria, the Norwegian client Statnett chose the Croatian Dalekovod company's offer, and the intention to conclude a contract was quickly expressed. At this moment in time, the appeal period is still running, and if there are no surprises or bumps in the road, Dalekovod's Management can peacefully wait for the conclusion of this important contract on the execution of works for this well-known partner.
They are just finishing the construction project of a new 420 kV transmission line between the substations Skillemoen and Skaidi for the aforementioned Norwegian client, which spans a total length of 89 kilometres and is specific given its geographical position in the far north of Norway. Because of that, it was built in arctic weather conditions.
Approximately 70 to 80 percent of the Croatian Dalekovod company's business revenues are generated on foreign markets. About 80% of that is realised in Scandinavia, which means that on an annual level, 50% of Dalekovod's income is generated by jobs carried out over o the Scandinavian market. Read More...